Unpaid on an Ontario construction job? What a subcontractor can ask for in writing
When a contractor says the owner has yet to pay, a written request can help you trace project payments while you check your lien deadline.
Suppose your framing crew finishes work on a Mississauga warehouse. Your invoice is overdue, and the general contractor tells you, “We’re still waiting for the owner to pay.” You have the delivery slips, time sheets and invoice. What you don’t have is a record of payments between the owner and the contractor.
Ontario’s Construction Act gives a subcontractor who has a lien a way to get some of those facts. A lien is a legal claim securing payment for work or materials supplied to a construction project. Under section 39(1), a person with a lien can make a written request for specific project information. The recipient must provide the information within a reasonable time, with an outside limit of 21 days. The right also extends to beneficiaries of a construction trust under Part II and to mortgage lenders. Read section 39 of the Construction Act.
Ask about the contract that matters to your invoice
In the warehouse example, the question is whether the owner has paid the general contractor. For a project the owner is building on its own land, you can ask either of them for the names of the parties to their contract, its price and a state of accounts. That last item is a dated breakdown that includes the value of work or materials supplied and the amounts paid. You can also ask for a copy of any labour and material payment bond the contractor posted with the owner. A bond may give eligible unpaid trades another route to payment, subject to its terms.
Now change one fact: a carpentry company hired your crew, and the general contractor hired that company. To find out what the general contractor paid the carpentry company, identify their subcontract in your request to the general contractor. A statement of what the owner paid under the main contract answers a different question. And even if the totals show that money changed hands, they may not tell you whether a particular payment covered your invoice.
Make the project easy to identify
Use your business’s legal name, the site address, the name of the company that hired you and a short description of what you supplied. For the first example, the request might read:
“Our company supplied framing labour at [project address] under our subcontract with [general contractor]. Under section 39(1) of the Construction Act, please provide the names of the parties to the owner–contractor agreement, the contract price, and a state of accounts as of a specified date. Please include a copy of any labour and material payment bond the contractor posted with the owner for this contract.”
Keep the request, a record of its delivery and any reply together. When you get the statement, check its date first. A statement prepared before your crew finished the framing may tell you very little about a payment the contractor says it received last week.
Check your lien deadline while you seek answers
Sending the request does not preserve a lien or extend the time for doing so. The 21 days concern the recipient’s response. Your own deadline can arrive sooner. If payment is overdue, pull together your subcontract, last supply records and any project notices promptly so a construction lawyer can check the applicable dates while you pursue the accounts. See the expiry rules in section 31 and the steps for preserving a lien in section 34.
Photograph by Vermont Timber Works Inc. Stack of Timber Bents, displayed with a landscape crop under CC BY-SA 3.0.
This article is general information and not legal advice. It does not create a lawyer-client relationship. A lawyer-client relationship begins only after a conflict check is completed, KS Legal agrees to act, and a retainer agreement is signed. Past outcomes do not guarantee future results.