An Ontario construction invoice is missing information. How long does the owner have to respond?
A missing purchase order and a disputed coat of paint call for different notices. See how Ontario’s seven-, 14- and 28-day rules work together.
A contractor sends a progress invoice for painting a new warehouse in Mississauga. The owner’s bookkeeper spots a missing purchase order number and puts the invoice aside until the next payment run. On a project covered by Ontario’s prompt payment rules, that delay can matter. Since January 1, 2026, an owner who receives a deficient invoice has seven days after receipt to tell the contractor in writing what is missing and what will fix it. Otherwise, the Act treats the invoice as a proper invoice for prompt payment purposes. See section 6.1 of Ontario’s Construction Act.
Identify what the contractor actually needs to correct
Start with the contract and the invoice side by side. Can you identify who did the work, the agreement that authorized it, the period or milestone being billed, what was supplied, the amount, the payment terms and where to send payment? Check any applicable contractual requirements and any information the owner reasonably requested for its accounts payable system.
In the warehouse example, a purchase order number is one way to identify the contract. If the invoice already identifies the agreement another way, check whether the number itself was required before treating its absence as a defect. If the contract requires the number and the contractor omitted it, a useful note would say, “Invoice 47 for the warehouse painting is missing the purchase order number required by our agreement. Please add PO-318 and return the corrected invoice to the project billing address.” Keep both versions and a record of when each was received.
A disagreement about the work needs a different response
Suppose the invoice contains all the required details, but the owner says the contractor billed for a second coat in a room that has only been primed. Now the question is how much the contractor has earned. To withhold a disputed amount under section 6.4, the owner must give the contractor the prescribed notice of non-payment within 14 days after receiving the proper invoice. The notice must specify the amount withheld and give every reason for withholding it. Ontario Court Services publishes the owner’s notice as Form 1.1. Find the Owner Notice of Non-Payment in the official forms list.
If $18,000 is payable after the applicable holdback and the owner disputes $3,000, a timely notice covering that $3,000 leaves $15,000 payable within 28 days after receipt of the proper invoice. The holdback is the amount retained under the Act to protect lien claims. The seven-day period for pointing out an invoice defect does not add seven days to the deadline for disputing payment. Read the owner’s payment and notice obligations in section 6.4.
For the next invoice, record when it arrived and send it that day to both the person who checks the paperwork and the person who inspects the work. Those people may have different answers. Keeping both responses with the invoice gives the owner time to identify a missing detail, document a disputed charge and pay the amount owing. For older projects, check when procurement began and when the contract was signed because the Act has transition rules. See the Act’s transition provisions.
Featured photograph by whereareyousimon. Tray, brush, roller, paint, displayed with a landscape crop under CC BY 2.0.
This article is general information and not legal advice. It does not create a lawyer-client relationship. A lawyer-client relationship begins only after a conflict check is completed, KS Legal agrees to act, and a retainer agreement is signed. Past outcomes do not guarantee future results.