Can an Ontario supplier claim a construction lien for materials left off site?

A driver unloads next door because the job site is blocked. Here is how Ontario’s lien rules treat that delivery and what the supplier should record.

November 15, 20262 min read
Pallets of red bricks wrapped for delivery beside stacks of concrete blocks

A brick supplier’s truck arrives at a Mississauga renovation. The driveway is blocked, so the masonry subcontractor directs the driver to unload in the lot next door. If the supplier goes unpaid, can those pallets count toward a construction lien on the renovation property? In Ontario, they can. What matters is who chose the drop location, how close it was to the job and which project the bricks were for.

When the delivery ticket shows a different address

Ontario’s Construction Act gives a supplier a lien for the price of qualifying materials supplied to an improvement for an owner, contractor or subcontractor. A lien is a claim against the owner’s interest in the improved property. In this example, the brick order is for the renovation. Storing the pallets next door does not, by itself, give the supplier a lien against the neighbour’s lot. Section 14 of the Construction Act.

The Act recognizes delivery onto the project land itself. It also recognizes delivery onto land in the immediate vicinity when the owner or the owner’s agent selected that land. For this purpose, the contractor or subcontractor receiving the materials can designate the spot as the owner’s agent unless the supplier has actual notice to the contrary. In the driveway example, save the mason’s text directing the driver next door. A delivery ticket showing only the neighbour’s street number leaves out the fact that explains the drop. See sections 1(2) and 1(3).

What if the bricks went to a warehouse?

Change one detail. The same mason orders four pallets for two renovations and sends them to a central warehouse across town. The warehouse receipt proves the mason received four pallets. On its own, it tells you little about which property received which bricks. The Act also recognizes materials incorporated into the work, used to carry it out or used to help carry it out directly. If two pallets later went into the wall at the Mississauga address, a transfer ticket and the mason’s site records could connect that quantity to the job.

What to put on the delivery record

Give the driver two fields to complete: the address of the project and the actual unloading location. If the truck is redirected, record who gave the instruction and keep the message with the signed ticket. For a split load, list the quantities for each job and keep any return or credit slip alongside the original order. Those details let someone reviewing the account match an unpaid amount to a particular property.

If payment is overdue, send the order, dispatch instructions, delivery tickets and account statement to your lawyer promptly. Identifying a qualifying delivery answers one part of the lien question. Your lawyer will also need the project dates and contract history to determine the deadline for preserving the claim.

Featured photograph by Shixart1985, resized and cropped for display. Bricks and concrete blocks at a construction site · CC BY 2.0.

This article is general information and not legal advice. It does not create a lawyer-client relationship. A lawyer-client relationship begins only after a conflict check is completed, KS Legal agrees to act, and a retainer agreement is signed. Past outcomes do not guarantee future results.