An Ontario construction lien was vacated from title. Is the payment claim over?
When security replaces a construction lien on title, the payment dispute can continue. Learn what owners and contractors should check in the court order.

Not necessarily. If an Ontario construction lien is removed from title after money is paid into court or security is posted, the lien claim can continue against that substitute security. Clearing the property’s title is not the same as deciding who owes what.
That distinction matters to a contractor waiting for payment and to an owner trying to deal with a property while an invoice dispute continues.
What does vacating a lien accomplish?
Section 44 of Ontario’s Construction Act provides a process for vacating a registered lien through payment into court or posting security. Under section 44(6), the lien moves from the premises to the money or security. Section 44(9) allows the claimant to continue an action to enforce the claim against that fund or security.
“Security” here means financial backing for the claim while the dispute is resolved. Posting it does not itself pay the claimant or establish that the claimed amount is correct.
In a hypothetical example, a contractor registers a lien for disputed renovation charges. The owner obtains an order under section 44 and posts the required security. The registration can be removed from title while the parties continue to dispute the invoice. Neither side should treat that title change as a final ruling on the bill.
Read the order, not just the title search
There are different reasons a lien registration might disappear. An order vacating it against security has a different effect from a settlement, release or order dealing with an expired lien. Ask your lawyer to review the actual documents before drawing conclusions.
Gather these records for that review:
- The registered claim for lien and any certificate of action.
- The court order and evidence of the money or security posted.
- The construction contract, invoices and payment history.
- Any settlement correspondence, release or other court documents.
For an owner, identify exactly which lien the order addresses and whether there are other registrations or claims that need attention. For a claimant, confirm what security now supports the claim and what procedural steps remain.
Do not assume deadlines have stopped
Have counsel confirm the next filing or litigation deadline as soon as the order arrives. Do not put the file aside because the property no longer shows the registration. Keep the evidence supporting the work and amount claimed organized while the dispute proceeds.
The statutory security calculation and the appropriate court process also need review for the particular project. Do not substitute the invoice amount for a lawyer’s calculation of what must be posted, or assume the funds are immediately available for withdrawal.
KS Legal assists owners, contractors and other construction participants in Mississauga and Ontario with construction lien matters. A review of the order and underlying claim can clarify what the title change actually means for the next step.
This article provides general information about Ontario law, not legal advice about a particular lien or court order.