Asked to sign a lien waiver before payment on an Ontario construction job?
Ontario prohibits contracting out of Construction Act protections, but discharging an existing lien is different. Check the paperwork before signing.
Do not assume that a document labelled “lien waiver” is harmless—or that its title tells you what it does. Ontario’s Construction Act prevents parties from contracting out of its protections, but discharging an existing lien is a different step with serious consequences.
What the Act says about waiving rights
Section 4 of the Construction Act makes an agreement void if a person supplying services or materials to an improvement agrees that the Act does not apply to them, or that its remedies are unavailable to them. An improvement is the construction project to which the work or materials relate.
That protection is not a reason to sign first and ask questions later. Have the whole document reviewed, including any statements about amounts received, work completed or claims being settled.
A discharge is not just another waiver
Under section 48, a lien discharged under Part VIII cannot be revived. The section preserves the possibility of a lien for services or materials supplied after the discharged lien was preserved; it does not restore the discharged lien for earlier work.
Hypothetical example: A Mississauga subcontractor has registered a lien for unpaid work. The contractor sends paperwork asking for a discharge now and promises payment next week. The subcontractor should get legal advice on the documents and payment arrangements before authorizing a discharge. Section 4 should not be treated as a way to undo it later.
Questions to resolve before signing
Send your lawyer the proposed document with the contract, invoices, payment history and any registered lien. Flag these questions:
- Is this an acknowledgement of payment, a release of claims, an agreement about future rights, or an authorization to discharge a lien?
- Which invoices, dates and amounts does it cover?
- Does it say you have been paid when money has not yet arrived?
- Does the wording include disputed extras or amounts you still expect to collect?
- How will payment and the release of documents be coordinated?
A reconciliation can help: list each invoice, payments actually received and the balance you say remains due. Attach supporting records rather than relying on the amount shown in the proposed form.
Keep deadlines on a separate track
Ask your lawyer to confirm any lien-preservation and enforcement deadlines while payment discussions continue. Do not assume that exchanging drafts or receiving a promise of payment protects your position.
KS Legal assists with construction-lien matters in Mississauga and Ontario. Have payment paperwork reviewed before signing, especially when a lien is already registered. This article provides general legal information; the effect of a particular document depends on its wording and the surrounding facts.
Photo: Stacks of red bricks and concrete blocks at a construction site during the day in an urban environment by Nenad Stojković (Shixart1985), under CC BY 2.0. Resized; the website may crop the photograph for display.
This article is general information and not legal advice. It does not create a lawyer-client relationship. A lawyer-client relationship begins only after a conflict check is completed, KS Legal agrees to act, and a retainer agreement is signed. Past outcomes do not guarantee future results.